Hydraulic activities began with the rehabilitation and extension of the water network of Yelimane, the capital of the district (project 1).
The accurate assessment of water supply needs was made by Veoliaforce volunteers with the support of the Solidarity Eau Program. After two years of study and joint discussions with the various beneficiaries of the project, the operations undertaken between 2006 and 2007 helped to rehabilitate and extend the historic water network of Yelimane dating back to 1956 and representing a distance of 6 kilometers.
In the resource itself, the main well was rehabilitated and a second well connected.
The water tower was reconditioned and the operating building extended with an additional room, to accommodate a chlorination unit. Eighty individual subscriptions were replaced with the installation of an individual meter for each. At the same time, the distribution network was extended four kilometers to the three neighboring villages (Yelimane Cebe, Dougoubara, Diadji). Finally, a total of 9019 linear meters of pipes were laid, thanks mainly to the work of the villagers. Twenty standpipes were installed, including six new ones for the three hamlets connected.
The accompaniment aspect consisted of the reorganization of the management committee, from the members making it up to the managing team, all working alongside the mayor of the commune.
Operations continued with the interconnection of the drinking water network between the villages of Gory Banda and Yaguine Banda, 15 km from Yelimane (project 2).
In order to cover the water needs of the villages, the technical partners were asked for expertise on two occasions to estimate the production capacity of the existing boreholes. These tests, financed by the association of the inhabitants of the villages culminated in a technical proposal around two boreholes, which were equipped with poorly functioning hand pumps. The proposal did not satisfy the requests for private connections made by the migrants, even though the studies immediately included the possibility of doing that subsequently, once the management and operation of the service was demonstrated for some time (at least one year). In fact, the forthcoming increase in water demand was considered with the immediate connection of a second borehole and the construction of a sufficiently large reservoir.